Wentzville Parkway South Phase 2

Project Status

Phase 2:
The Wentzville Parkway South Phase 2 improvement project will build upon the Wentzville Parkway South Phase 1 project by extending Wentzville Parkway South to Interstate Drive. The proposed cross-section will include a two-lane cross-section with curb and gutter and curb inlets along the east side of the roadway and an improved shoulder on the west side that will drain to an open ditch system. The cross-section will allow for future expansion to a five-lane cross-section when traffic demands call for it. The proposed project also proposes to build a 6-foot sidewalk along the east side of the roadway that will connect to the recently constructed Interstate Drive Trail. Also proposed as part of this project is the construction of a grade-separated crossing at the Norfolk Southern Railway.

May 2019: A notice to Proceed was issued to the design consultant.

January 2020: Preliminary Plans completed.

August 2020: Right of Way Plans completed and the land acquisition process has begun.

December 2021: Final Bridge Plans have been submitted to Norfolk Southern Railroad for review. Right of Way acquisition process is ongoing.

April 2022: Continued Right of Way acquisition and Final Plans. 

March 2023: Continuing Right of Way acquisition and Final Plans.

June 2023: Right-of-way acquisition is still underway. Final Plans are being reviewed by
Norfolk South Railroad for final approval.

November 2023: Right-of-way acquisition is still underway. The Norfolk Southern Railroad Construction Agreement has been fully executed. Final Plans have been approved by NS Railroad.

August 2024 – Final Plans are being finalized. The city is working with Norfolk Southern Railroad on the final easement documents. Utility relocation coordination is taking place.

Anticipated Construction Spring 2025.

For questions, please contact Tony Gambaro, Engineering ManagerĀ at (636) 639-2053 or by email Tony.Gambaro@wentzvillemo.gov