The City of Wentzville will hold an open-house public meeting on July 31, 2024, to discuss the Mexico Road Safety Improvements Project. This proposed project will resurface the existing Mexico Road approximately between Josephville Road to Brookview Way Drive, widen shoulders, re-align the intersection at Hancock Road and add an additional sidewalk from Lakeview Elementary School to Westwind Park Drive. To view the rough drafts click here.
The public open house is scheduled for Wednesday, July 31 from 4:30-6:30 p.m. at the Wentzville City Hall Board Chambers, 1001 Schroeder Creek Blvd., Wentzville MO.
Current project status:
August 2024: ROW acquisition is underway.
For questions about this project please contact Alex Kreke (636) 639-2168 or by email Alex.Kreke@wentzvillemo.gov.
This project involves the improvements of the intersection at West Pearce Boulevard and North Linn Avenue from an all-way stop intersection to a signal control intersection while improving pedestrian connectivity with sidewalk replacements, curb ramps, crosswalks, and ADA-compliant push buttons.
This project is funded by the City of Wentzville Transportation fund, St. Charles County Transportation Sales Tax Funds, and the Federal Highway Administration (FHWA) Congestion Mitigation and Air Quality (CMAZ) Improvement program funding. The Engineer design consultant is George L Crawford and Associates d/b/a CBB.
CLICK THE THUMBNAIL TO VIEW THE FULL-SIZE RENDERING.
The City of Wentzville will hold an open-house public meeting on Feb. 2, 2023, to discuss the Peine Road Safety Improvements Project. This proposed project will resurface the existing Peine Road approximately between Stewart Springs Drive and Forest Way, add shoulders, and soften and realign a 90-degree curve between Peine Woods Drive and Stewart Springs Drive. This project will look to address safety conditions in advance of the increased traffic volume anticipated with a completed Peine/Hwy P Interchange as well as ongoing development along the Peine Road corridor. Construction of this project is tentatively scheduled to begin in 2024.
The public open house is scheduled for Thursday, February 2, 2023, from 4:30 p.m. to 6:30 p.m. at the Wentzville City Hall Board Chambers, 1001 Schroeder Creek Blvd, Wentzville, MO.
CLICK THE THUMBNAIL TO VIEW THE FULL-SIZE RENDERING.
This project is funded by the Department of Transportation, Federal Highway Administration Surface Transportation Program, the St. Charles County Road Board and the City of Wentzville.
Northbound Route Z Right Turn Lane at Interstate Drive: This project will construct a dedicated Northbound Route Z right turn lane to eastbound Interstate Drive. This widening will be between the northern limits of the bridge of Pereque Creek and Interstate Drive. There will also be a 4-foot shoulder added to help bicyclists on Route Z access the Interstate Drive 10-foot multi-use trail.
November 2021: Design work for Right Turn Lane has been incorporated into the more recent Route Z and Interstate Drive Intersection Improvement project that widens the remaining 3 legs of the intersection.
May 2023: This project is being incorporated into Route Z and Interstate Drive Intersection Improvement Project. Final Plans have been submitted to MoDOT for final approval to allow for bidding on the project.
August 2024 – The project is complete.
Route Z and Interstate Drive Intersection Improvement Project: This project with construct dual left turn lanes from eastbound Interstate Drive to Northbound Route Z, a dedicated southbound Route Z right turn lane to westbound Interstate Drive and Northbound Route Z will also be restriped to 2 northbound lanes from Interstate Drive to the Eastbound I-70 on-ramp. The southern leg of the intersection will also be improved to accommodate 2 southbound Route Z lanes for the future widening of Route Z.
March 2021: City entered into a funding agreement with St. Charles County fund the use of St. Charles County Transportation Sales Tax Funds. The city entered into an agreement with Missouri Highway and Transportation Commission for CMAQ funds.
June 2021: City selected a design consultant and entered in an agreement with Oates Associates for the design of this project.
November 2021: Conceptual design plans were submitted to the City for review and comment.
June 2022: MoDOT approved the Right of Way Plans and gave the Notice to Proceed for ROW Acquisition.
July 2022: Right of Way Acquisition meetings with property owners have begun. Design plans are continuing with utility relocation coordination.
May 2023: Final Plans have been submitted to MoDOT for final approval to allow bidding on the project.
August 2024 –Theproject is complete.
Route Z Widening and Signalization (Interstate Drive to Perry Cate Blvd): This project will widen Route Z to a 4-lane facility south of Interstate Drive to Perry Cate Boulevard with dedicated left-turn and right-turn lanes at key side streets. Associated with this widening is also the widening/ replacement of the bridge over Peruque Creek to accommodate the 4-lane cross-section and the extension of a multi-use trail. The existing 3-foot paved shoulders will be replaced with 6-foot wide shoulders. In addition to the pavement and bridge widening, this project also will be adding a traffic signal at the intersection of Route Z and Peruque Hills Parkway/ Peruque Ridge Boulevard.
September 2021: The City of Wentzville entered into a project agreement with MoDOT for Cost Share funding and local maintenance funds.
February 2022: The City of Wentzville entered into a project agreement with St. Charles County for use of St. Charles County Road Board Funds.
May 2022: City selected a design consultant and entered into an agreement with Oates Associated for the design of this project.
July 2022: The design Contract is being approved by MoDOT with the obligation of MoDOT funding. Will anticipated the design to begin in August.
May 2023: Preliminary Plans are being drafted. Anticipate and Public Meeting fall 2023 for the project.
August 2024 – Working on scheduling a Public Open House meeting to display the improvement plans and take comments
For questions regarding these projects please contact Tony Gambaro, Engineering Manager Tony.Gambaro@wentzvillemo.gov
Phase 2: The Wentzville Parkway South Phase 2 improvement project will build upon the Wentzville Parkway South Phase 1 project by extending Wentzville Parkway South to Interstate Drive. The proposed cross-section will include a two-lane cross-section with curb and gutter and curb inlets along the east side of the roadway and an improved shoulder on the west side that will drain to an open ditch system. The cross-section will allow for future expansion to a five-lane cross-section when traffic demands call for it. The proposed project also proposes to build a 6-foot sidewalk along the east side of the roadway that will connect to the recently constructed Interstate Drive Trail. Also proposed as part of this project is the construction of a grade-separated crossing at the Norfolk Southern Railway.
May 2019: A notice to Proceed was issued to the design consultant.
January 2020: Preliminary Plans completed.
August 2020: Right of Way Plans completed and the land acquisition process has begun.
December 2021: Final Bridge Plans have been submitted to Norfolk Southern Railroad for review. Right of Way acquisition process is ongoing.
April 2022: Continued Right of Way acquisition and Final Plans.
March 2023: Continuing Right of Way acquisition and Final Plans.
June 2023: Right-of-way acquisition is still underway. Final Plans are being reviewed by Norfolk South Railroad for final approval.
November 2023: Right-of-way acquisition is still underway. The Norfolk Southern Railroad Construction Agreement has been fully executed. Final Plans have been approved by NS Railroad.
August 2024 – Final Plans are being finalized. The city is working with Norfolk Southern Railroad on the final easement documents. Utility relocation coordination is taking place.
Anticipated Construction Spring 2025.
For questions regarding this project please get in touch with Tony Gambaro, Engineering Manager Tony.Gambaro@wentzvillemo.gov
4/30/2019 – Open House Public Meeting held at Wentzville City Hall from 4:00 pm to 7:00 pm. Staff from the City of Wentzville were on hand to answer questions and showcase the City of Wentzville’s US 61 West Outer Road Phase 2, 2A, and 3 proposed project. Also on hand were staff from St. Charles County Highway and the Missouri Department of Transportation to showcase and answer questions regarding a conceptual plan to extend an outer road system on US 61 North between Route P/Peine Road and the Lincoln County/St. Charles County line. Exhibits and fact sheets from the meeting can be found below.
November 2021: The phase 2A project has been awarded federal funds from East-West Gateway and County Road funds from St. Charles County Road Board. The project will be moving into the Right of Way acquisition phase in late 2022.
June 2023: The Phase 2A project, Wentzville Parkway Turn Lane, Meyer Road to Parkway Ridge Boulevard has received MoDOT environmental clearances and is awaiting approval for the Right of Way plan. Right of Way acquisition will continue through 2023.
August 2024 – The Phase 2A project, Wentzville Parkway Turn Lane Project (Meyer Road to Parkway Ridge), ROW acquisition is complete. Final plans are being finalized and will be submitted to MoDOT for review and approval in the next couple of months.
Anticipated Construction Spring 2025.
For questions, please contact Matt Wohlberg, Director of Engineering at 636-327-5101 or email matt.wohlberg@wentzvillemo.gov.
Description: A consultant is providing additional analysis to supplement the Wentzville Parkway South Extension Corridor Study completed in early 2013. A corridor alignment that is supported by the local governments and citizens is essential for the corridor preservation process. The intent of the study is to engage the public in developing solutions and to accurately define future construction costs of the project and preserve land prior to future development.
The City of Wentzville in cooperation with the County of St. Charles have coordinated to supplement the initial Study to consider an at grade railroad crossing, improvements to the Wentzville Parkway Interchange, traffic signal optimization and traffic flow improvements from Veterans Memorial Parkway to the traffic signal in front of Home Depot. In summary, the objectives of the Supplemental Study are to establish a feasible, cost effective and locally supported interchange with Interstate 70, determine the feasibility and cost of an at grade crossing for the Norfolk Southern Railroad, and recommend traffic flow improvements of the section of Wentzville Parkway immediately north of the Interstate 70 interchange.
David Hoekel Parkway Phase 2D will be a north-south roadway of approximately 5,500 linear feet along an existing 100-foot wide City of Wentzville right-of-way corridor. Once completed, this roadway will help alleviate congestion and convey motorists to and from Interstate 70 to West Meyer Road. This project will complete the final segment of David Hoekel Parkway Phase 2.
Phase 2D of David Hoekel Parkway (DHP) includes roadway improvements along the planned DHP corridor between Goodfellow Road and West Meyer Road. This phase of the project will build upon previous phases of DHP by connecting West Meyer Road to the I-70 interchange at DHP and to the south side of the interstate. The proposed project will construct two lanes of DHP on the eastern side of the corridor, one northbound lane and one southbound lane. The ultimate DHP build-out will consist of a four-lane divided roadway. The timeline for the final corridor buildout is currently undetermined and will be based on future traffic demands. The current phase of this project also includes a sidewalk, which will connect pedestrians to the trail that was recently constructed with the West Meyer Road improvements and to the sidewalk being constructed with the David Hoekel Parkway bridge over I-70.
Timeline of the David Hoekel Parkway When available, please see the underlined dates for additional project details.
August 2024: Construction is ongoing. Pavement is being installed from Bear Creek Drive to West Pearce Blvd. Crews are working on installing street lighting from West Meyer Road to Bear Creek.
Tentative Completion Late 2024.
2023: Grading and Construction of Drainage Facilities
2022: Easement & Right of Way Acquisition
2020-2021: The City entered into a funding agreement with St. Charles County for the final design and construction of Phase 2D of David Hoekel Parkway. The City retained the services of a design firm to prepare plans and specifications for this project. The noise study has been re-evaluated with the preparation of plans for construction.
2018: The City retained the services of a design firm to evaluate this David Hoekel Parkway Phase 2D corridor and provide the City with conceptual plans, cost estimates, traffic circulation reports and a sound wall analysis. During this Phase 2D corridor evaluation, the City evaluated whether the previously recommended four-lane median-divided configuration identified within the David Hoekel Parkway Environmental Assessment that was completed in November of 2014 was still valid for initial construction or if a reduced two-lane cross-section might instead be adequate to serve the anticipated future traffic volumes. The report confirmed that David Hoekel Parkway Phase 2D’s ultimate cross-section shall provide a four-lane median divided cross-section as previously recommended by the David Hoekel Parkway Environmental Assessment but current and near-future traffic volumes only require a two-lane cross-section to be built at this time. As a continuation of the current David Hoekel Parkway Phase 2C project (Interstate 70 north to Goodfellow Road), the traffic circulation report also confirmed that building the eastern half of the ultimate roadway cross-section (the northbound lanes) with northbound and southbound left-turn lanes at both Bear Creek Drive and Kruger Park Court intersections was recommended until traffic volumes require the additional two lanes (the southbound lanes) to be constructed.
2014: The U.S. Department of Transportation (Federal Highway Administration) approved the City’s proposal to design and construct a new interchange along the I-70 corridor as part of the David Hoekel Parkway designated as Phase 2A, B, & C. The interchange project is expected to be completed Summer of 2021. Phase 2A, B, & C included the interchange at Interstate 70 and a realigned North Outer Road as well as the intersection of David Hoekel Parkway and Goodfellow Road/North Outer Road. The David Hoekel Parkway Phase 2D project will begin at this intersection and proceed north to tie in with West Meyer Road.
2009-2014: The City submitted a draft Environmental Assessment to the U.S. Department of Transportation Federal Highway Administration (FHWA). This document considered and evaluated project alternates and environmental consequences for impacts to land use, water quality, cultural resources, threatened and endangered species, air quality, noise and construction impacts among other factors. The FHWA issued approval of the Environmental Assessment and issued a Finding of No Significant Impact.
2003: The Corridor Preservation Study allowed the City to coordinate with proposed and planned development to preserve the Right of Way.
2001: The City studied a corridor (several alignments) and involved the public for comment which identified this corridor called the “I-70/US 61 Beltway Corridor Preservation Study.”
1999: The City first adopted a Comprehensive Plan identifying the need for a new roadway.
For questions regarding this project please contact Tony Gambaro, Senior Project Manager, by email at Tony.Gambaro@wentzvillemo.gov.