U.S. 61 West Outer Road Extension Phases 2 and 3
Project Status
-
Planning
Planning
-
Environmental
Environmental
-
Design
Design
-
Construction
Phase
-
Completion
Phase
4/30/2019 – Open House Public Meeting held at Wentzville City Hall from 4:00 pm to 7:00 pm. Staff from the City of Wentzville were on hand to answer questions and showcase the City of Wentzville’s US 61 West Outer Road Phase 2, 2A, and 3 proposed project. Also on hand were staff from St. Charles County Highway and the Missouri Department of Transportation to showcase and answer questions regarding a conceptual plan to extend an outer road system on US 61 North between Route P/Peine Road and the Lincoln County/St. Charles County line. Exhibits and fact sheets from the meeting can be found below.
November 2021: The phase 2A project has been awarded federal funds from East-West Gateway and County Road funds from St. Charles County Road Board. The project will be moving into the Right of Way acquisition phase in late 2022.
June 2023: The Phase 2A project, Wentzville Parkway Turn Lane, Meyer Road to
Parkway Ridge Boulevard has received MoDOT environmental clearances and is
awaiting approval for the Right of Way plan. Right of Way acquisition will continue
through 2023.
August 2024 – The Phase 2A project, Wentzville Parkway Turn Lane Project (Meyer Road to Parkway Ridge), ROW acquisition is complete. Final plans are being finalized and will be submitted to MoDOT for review and approval in the next couple of months.
January 2025 – The Phase 2A, Wentzville Parkway Turn Lane Project (Meyer Road to Parkway Ridge), MoDOT has approved the PS&E plans and construction bidding will take place within the next month. Utility relocation work has begun.
For questions, please contact Matt Wohlberg, Director of Engineering at