The Wentzville Water Division will execute urgent repair work on the City’s main water supply transmission main beginning Monday, March 30. This work is taking place before the peak summer usage months to reduce potential impacts on customers; however, customers may still experience reduced pressure during the repair period. We anticipate the repair will be complete within 72 hours. If you have questions, please call (636) 639-2121 during regular business hours.

 

Wentzville Parkway Turn Lane Phase 2A

Project Status

This project consists of full pavement replacement and widening between Meyer Road and Parkway Ridge Boulevard (near QT). In addition, a sidewalk and multi-use trail will be constructed on the north and south sides of the roadway with continuous street lighting.

Project updates:

November 2021-The phase 2A project has been awarded federal funds from East-West Gateway and County Road funds from St. Charles County Road Board. The project will be moving into the right-of-way acquisition phase in late 2022.

June 2023- The Phase 2A project, Wentzville Parkway Turn Lane, Meyer Road to
Parkway Ridge Boulevard has received MoDOT environmental clearances and is
awaiting approval for the right-of-way plan. Right-of-way acquisition will continue
through 2023. 

August 2024 – The Phase 2A project, Wentzville Parkway Turn Lane Project (Meyer Road to Parkway Ridge), ROW acquisition is complete. Final plans are being finalized and will be submitted to MoDOT for review and approval in the next couple of months. 

January 2025 – The Phase 2A, Wentzville Parkway Turn Lane Project (Meyer Road to Parkway Ridge), MoDOT has approved the PS&E plans and construction bidding will take place within the next month. Utility relocation work has begun.

May 2025- Construction will begin on the Phase 2A project, Wentzville Parkway Turn Lane Project. Wentzville Parkway will be reduced to one lane in each direction for most of the project to accommodate full pavement replacement.

August 2025– Construction continues on the pavement replacement; Four of the five lanes have been completed to date. Wentzville Parkway continues to be reduced to one lane in each direction during the pavement replacement. The crew will then begin working on sidewalks, lighting, and restoration work through the fall. 

 December 2025  – Project is complete. 

For questions, please contact Matt Wohlberg, Director of Engineering at 636-327-5101 or email matt.wohlberg@wentzvillemo.gov.