Wentzville Parkway South Phase 2

Phase 2:
The Wentzville Parkway South Phase 2 improvement project will build upon the Wentzville Parkway South Phase 1 project by extending Wentzville Parkway South to Interstate Drive. The proposed cross-section will include a two-lane cross-section with curb and gutter and curb inlets along the east side of the roadway and an improved shoulder on the west side that will drain to an open ditch system. The cross-section will allow for future expansion to a five-lane cross-section when traffic demands call for it. The proposed project also proposes to build a 6-foot sidewalk along the east side of the roadway that will connect to the recently constructed Interstate Drive Trail. Also proposed as part of this project is the construction of a grade-separated crossing at the Norfolk Southern Railway.

CLICK THE THUMBNAIL TO VIEW THE FULL-SIZE RENDERING.

Screenshot 2023-03-06 at 3.52.33 PM - Copy (2)

May 2019: A notice to Proceed was issued to the design consultant.

January 2020: Preliminary Plans completed.

August 2020: Right of Way Plans completed and the land acquisition process has begun.

December 2021: Final Bridge Plans have been submitted to Norfolk Southern Railroad for review. Right of Way acquisition process is ongoing.

April 2022: Continued Right of Way acquisition and Final Plans. 

March 2023: Continuing Right of Way acquisition and Final Plans.

June 2023: Right-of-way acquisition is still underway. Final Plans are being reviewed by
Norfolk South Railroad for final approval.

November 2023: Right-of-way acquisition is still underway. The Norfolk Southern Railroad Construction Agreement has been fully executed. Final Plans have been approved by NS Railroad.

Anticipated Construction to Begin Spring 2024

For questions regarding this project please contact Tony Gambaro, Engineering Manager Tony.Gambaro@wentzvillemo.gov

bg

Stay Up to Date
Sign up for our eNewsletter