West Pearce Blvd. (1-70 North Outer Road) Resurfacing Project

The West Pearce Boulevard Resurfacing Project consists of adding a 2-foot aggregate pavement edge treatment/ shoulders and resurfacing the West Pearce roadway from May Road to approximately 850 feet west of North Point Prairie Road. This project also will complete any necessary full-depth pavement repairs, replacement/ installation of new fencing with glare slates, centerline rumble strips, and upgrading of any deficient signing and guardrail.

February 2020 – The City of Wentzville entered into a program agreement and the Missouri Highway and Transportation Commission for federal funding

January 2021 – City has selected a consultant and entered into an agreement for the design work.

September 2021 – MoDOT approved the Preliminary Design Plans.

October 2021 – Submitted Right of Way Clearance to MoDOT for approval.

November 2021 – Pavement boring was completed and design work is ongoing.

July 2022- Final design plans are being drafted and reviewed by city staff.

September 2022- City submitted Final Plans and Bid Documents to MoDOT for approval. The city anticipates bidding in December 2022 with a project award in January 2023.

November 2022 – Bid Documents still awaiting MoDOT approval. City anticipates bidding
December 2022 with project award in January 2023.

June 2023 – The contractor has started the construction of the aggregate shoulders. Pavement
repairs will be taking place at the end of June. Asphalt operations will be starting in July.

 For questions regarding this project please contact  Alex Kreke, Senior Civil Engineer at Alex.Kreke@wentzvillemo.gov