Phase 1:
The interchange improvements to Wentzville Parkway at I-70 will remove the existing eastbound on-ramp and fold it to move the ramp terminal to the outer road. Traffic southbound on Wentzville Parkway attempting to head east on Interstate 70 will make a right turn at the south outer road (Veterans Memorial Parkway), and then a U-Turn at a proposed roundabout to access the interstate. This configuration allows the predominate movement at the interchange, southbound to eastbound, to be performed through a series of right turns, rather than a left turn at a signalized intersection. The relocations of the eastbound on-ramp also allow for a longer acceleration lane for this movement in advance of a curve along the interstate.

CLICK THE THUMBNAIL TO VIEW THIS DIAGRAM

PLAN_WPSPh1_Stage4Map_20230929 - Traffic Lines - Copy


May 2019: A notice to Proceed was issued to the design consultant.

March 2020: Preliminary Plans approved by MoDOT.

August 2020: Right of Way Plans approved by MoDOT.

January 2021: Right of Way Acquisition has continued and will anticipate a late Spring/ Early
Summer Construction Contract Bid.

December 2021: Right of Way Clearance submitted to MoDOT for approval.

April 2022: Final Plans and Bid Documents are being approved by MoDOT. Anticipated
Bidding of Project April/ May 2022.

July 2022: Construction Project was Bid and is in the process of being awarded. Construction is
scheduled to start late summer/ early fall 2022.

December 2022: Stage 1 construction has begun. The first stage should consist of 3 months of
work. Temporary pavement has been constructed on Veterans Memorial Parkway and temporary
concrete traffic barriers have been placed.  Temporary Ramp 2 off of EB I-70 is under
construction. Excavation and embankment for Veterans Memorial Parkway, the roundabout, and
the Backage Road are moving according to plan. Paving on the Backage Road has begun. 

March 2023: Crews are continuing to excavate and pave Stage 1 along Veterans Memorial
Parkway. The intersection of Veterans Memorial Parkway and Ruggeri Drive is closed while
crews reconstruct a new entrance. To access Bandana's BBQ and Extra Space Storage, use the new Backage Road that is directly west of BP. Expect to use this detour for the next 4 weeks.
Work on I-70 EB is anticipated to begin in 2 weeks. Temporary concrete barriers will be placed
and temporary striping will be installed to shift the 2 through lanes and narrow the lanes to allow
crews room to work on the south shoulder of I-70.

April 2023: Crews are continuing to excavate and pave Stage 1 along Veterans Memorial
Parkway. The Ruggeri Drive/BP entrance should be complete and open to traffic by Friday
March 21. The traffic switch from Stage 1 to Stage 2 is anticipated to be done the week of May
1 . During this time, for a short period of approximately 24 hours, Veterans Memorial Parkway
east of the Wentzville Parkway intersection will be closed. Work on I-70 EB has begun.
A temporary concrete barrier and temporary striping have been placed.

May 2023: Traffic has been moved onto the new pavement on Veterans Memorial Parkway.
Crews begin to excavate and pave Stage 2 along Veterans Memorial Parkway and the new I-70
EB deceleration lane.

June 2023: Crews will continue to pave Veterans Memorial Parkway west of Wentzville
Parkway.

July 2023: Crews continue to pave the remaining portions of Veterans Memorial Parkway and the new I-70 EB off-ramp. Utilization of the new off-ramp and the Roundabout is expected by the beginning of August. Additional information will be provided closer to the traffic switch.

August 2023: Traffic utilizing the new off-ramp and Roundabout. Crews will continue to construct the medians and islands near the roundabout.

September 2023: Crews continue to pave the new I-70 EB on ramps from VMP and the Roundabout. Utilization of the new on-ramps is expected by the first week of October. Additional information will be provided closer to the traffic switch.

November 2023: New EB On-Ramp has been fully opened. Crews are still working on grading and removal of the old EB on the ramp area. Crews will be working on final signing, lighting and restoration work throughout the next few weeks. Crews are also working on pavement replacement on Ruggeri Drive near Bandana's Bar-B-Q.

 


For questions regarding this project please contact Matt Davidson, Senior Civil
Engineer at Matt.Davidson@wentzvillemo.gov